So, it's been a long and both exciting and frustrating weekend for things with the cabin.
On the exciting side, the hot tub is now up on the deck and in theory beyond a few things in the grand scheme of things the builder should have all of the materials now to essentially finish the cabin.
Unfortunately, there's a lot more to type about on the frustrating side of things.
First off, the GC got absolutely nothing done last week on the cabin despite the fact that the other job that has been getting in the way finishing up on Tuesday. We were expecting he'd be out there with his 'crew of 7 guys' starting Wednesday to get things moving now that both the electrical and plumbing inspections were done. Nope- today is the first day that he will be out there besides his tile guy being out last week pouring the base to the shower. While this would have been annoying under any circimstance given how long this has been taking, it was REALLY pissing us off because that meant that he had nobody there Saturday to help haul all of the aforementioned materials up the 50 stairs to the cabin.
Some background- as part of the contract, we're responsible for buying all of the materials excepting a few specific things (like the insulation). While it means more time we have to spend on things, we didn't totally complain because it meant that we had full accounting and transparency on the costs that we hadn't had with the previous builder. The annoying thing has been that the builder hasn't been the most willing to meet up with his big box truck to get the materials at the stores, so we've had to get them out to an hour away and up a really steep gravel road to the cabin itself. AND THEN, there's the 50 steps to climb to get anything into the cabin itself or up to the deck.
One of the reasons given why they hadn't been out working was because they needed materials, which he only sent us mid-last week. We had arranged with the guys to haul the hot tub up to the cabin to do so Saturday and said that we would bring the materials out then since we'd need a massive trailer for the hot tub anyway, so he had plenty of time to get at least a few guys together to schlep all of the stuff up the stairs. NOPE! Due to various reasons, he said he couldn't get anyone there Saturday to help with things.
So, no only did the Dancer and I have to spend most of Friday afternoon and evening getting and loading up everything into the 6'x12' UHaul trailer and the truck bed- building materials plus a 300lb+ hot tub and a stackable apartment-sized washer and dryer- but we were looking at having to get all of the materials up the stairs to the cabin itself (the hot tub and W/D were going to be hauled up by the guys we had coming specificall for that task).
To clarify the magnitude of this, here's some of the numbers I worked up based on what all we had to get-
- Approximately 1300 lbs of wood, including four 80lb treated 8-foot 6x6s that the Dancer and I struggled to simply MOVE together
- Almost 1000lbs of tile between the tile for the shower walls (11 60lb boxes...) and the cut pebble tiles for the shower floor and bathroom floor, plus dry (thankfully) grout and adhesive
- 14 cement backer boards, 7 36lb 1/2" and 7 20lb 1/4" thick
All told- roughly 1.5 TONS- literally- of materials that the contractor expected that a dance teacher and an engineer were going to carry up 50 stairs.
Thankfully they guys who were there to move the hot tub and W/D did us a MASSIVE solid and themselves moved the vast majority of the materials (and we left the things that we knew didn't have to go all the way up down at the bottom of the stairs for the contractor & crew to deal with, because berk that E36 M3). It's hard to believe that someone could put a 8-foot 6x6 topping out at 81lbs on their shoulder and carry it, alone, up 54 stairs- but they did so, twice each. They had to have made nearly 20 trips up the stairs carrying a minimum of 40lbs of materials each time. It was pretty humbling to be struggling with carrying a 60lb box of tiles up the stairs while they made over 10x as many trips carrying 25% more weight than I could.
But, it did all get moved, and we bumped up what we had planned to pay them for moving the tub and W/D because of the extra effort. As an interesting note, the main guy doing the tub move is the second contractor who I had come out to give a bid on finishing the cabin but who had ultimately declined to put in a bid. I'm much more seriously than before considering whether to ask if he'll give me an estimate on enclosing the framing under the cabin- it's expressly NOT in the contract with the current builder, and after this weekend I'm far less confident that I'd be able to do it myself given how badly just doing what I did this weekend kicked my ass.
Other than the whole issue with not having anyone out there, there was the issue of the contractor having a bit of a meltdown on the phone with the Dancer on Saturday. On Friday after hearing that he wouldn't she told him that we were getting a bit nervous about things because he kept saying that he'd have this 7-man crew out there to knock things out really fast but that never seemed to materialize and we were getting worried about how long it would be until it would finally be finished. When she called to let him know that everything was dropped off he went off about how he hadn't been able to sleep a wink the previous night because she'd said that we were 'nervous' about things and couldn't believe she'd said that and how NOONE had EVER had ANY problems with the work he'd done and how we kept asking him to do things that were not in the original contract (aside: yes- but more than half of those things were suggested BY HIM in the first place...) and that us bringing things like the W/D out was just getting in the way and he wasn't sure he wanted to spray the polyurethane on the inside walls now because he'd have to worry about getting it on the W/D... and on and on. I was sitting next to her in the truck for about half of the 'conversation' since we had stopped to pick up dinner, and it was pretty ridiculous. It was VERY similar to a completely ridiculous call from him back when he was working on putting the bid together. We're more than halfway convinced he has a bit of a mental issue (we have a friend who was bipolar, and this struck both of us as being similar to some incidents with her).
Of course, when we talked to him yesterday about some of the details for the shower that he was concerned about, everything was peachy and fine. Frankly at this point (and this would be the case even without the weird meltdown...) we just want things finished and his work out there done so we can actually enjoy the place. We REALLY wanted him to have it done by Labor Day since we both have it off and could likely get a bunch of friends together to help haul the furniture and such up to the cabin and then have a cabin-warming party with everyone, but he's convinced that won't happen (at least in part since he is apparently going on vacation in a week...). We don't see how things are going to take that long- he's said outright that the insulation will take like 2 hours do put in, and the shower and bathroom tiling isn't supposed to take more than 3 days (and is just one of his crew who will mainly be doing that).
We're planning on making an un-announced visit after work on Wednesday to see how things have gone the first half of this week... hopefully we see LOTS of progress, or we might have to upgrade from 'nervous' to 'frustrated'...